When a contractor sends you a quotation for a house in Rwanda, it usually comes as a Bill of Quantities, or BOQ. It is the most important document for controlling the cost of your build, yet many clients only look at the total at the bottom of the last page.
This guide explains what a BOQ is, what a complete one should contain, how to read a contractor’s priced BOQ line by line, and the warning signs to look for before you sign.
A Bill of Quantities is a list of every item of work and material needed to build a project, measured from the drawings and specifications. Each item has a description, a unit of measurement and a quantity. Contractors then add a rate to each item, and the rate multiplied by the quantity gives the amount.
A good BOQ does three jobs. It lets several contractors price exactly the same scope, so their quotes can be compared fairly. It becomes the basis for paying the contractor in installments as work progresses. And it gives you a reference for pricing changes if the design changes during construction.
The BOQ is only as reliable as the drawings behind it. If the architectural and structural drawings are incomplete, the quantities will be too. That is why the BOQ normally comes after the design is fixed and, ideally, after the construction permit has been approved, so the measured design is the one you are allowed to build.
BOQs are prepared by quantity surveyors. In Rwanda, the profession is organised by the Rwanda Institute of Quantity Surveyors (RIQS), which publishes a list of members in good standing and refers to Law n° 023/2025 of 01/09/2025 governing the professions of architecture, engineering and quantity surveying. Before relying on a BOQ for a significant project, it is reasonable to ask who measured it and whether they are registered.
For a typical house or small building, the BOQ is split into sections that follow the order of construction. The exact headings vary, but you should expect to see most of the following:
Material choices drive many of these lines. If you are comparing specifications for tiles, cement or steel, our guide to sourcing building materials in Rwanda explains what to check.
Every line of a priced BOQ follows the same pattern. The example below shows the structure of a few typical items. It is a format illustration only, so the rate and amount columns are left blank.
| Item | Description | Unit | Qty | Rate | Amount |
|---|---|---|---|---|---|
| A1 | Excavate foundation trenches not exceeding 1.5 m deep | m³ | measured | Rwf / m³ | Qty × Rate |
| B4 | High-yield reinforcement bars to columns, cut, bent and fixed | kg | measured | Rwf / kg | Qty × Rate |
| C2 | Walling in concrete blocks, bedded in cement mortar | m² | measured | Rwf / m² | Qty × Rate |
| F7 | Supply and fix internal flush door complete with frame and ironmongery | Nr | counted | Rwf / Nr | Qty × Rate |
When you review a priced BOQ, work through these checks:
The fairest way to compare contractors is to give all of them the same unpriced BOQ, prepared by your own quantity surveyor, and ask them to fill in the rates. You can then compare item by item instead of comparing totals built on different assumptions. If you are still shortlisting builders, our sister studio’s guide on how to choose a construction company in Kigali covers the other checks to make before you sign.
Once a BOQ is agreed, it becomes part of the contract. Installment payments are usually valued against the BOQ items completed on site, and any design change is priced as a variation using the agreed rates where they apply.
The BOQ covers the construction work. Your full budget also needs land, design fees, permits, connections and a contingency. Our article on what drives the cost of building a house in Rwanda walks through the other cost drivers to plan for.
This article is general guidance. For a specific project, have the BOQ prepared or reviewed by a qualified quantity surveyor.
A quotation can be a single total. A BOQ breaks that total into measured items with quantities and rates, so you can see exactly what you are paying for and compare contractors item by item.
Ideally your own quantity surveyor prepares an unpriced BOQ from the approved drawings, and contractors price it. A BOQ measured by the contractor is harder to compare with other bids.
The summary should state clearly whether VAT is included. Rwanda's standard VAT rate is 18% for VAT-registered suppliers.
Only a rough estimate. Accurate quantities need architectural and structural drawings, because the BOQ is measured from them.
Contractors are usually paid in installments valued against completed BOQ items, and design changes are priced as variations using the agreed rates.